Slough

28 Sep

Poyle 14 - Slough
 
Drylining = 3025 LM
Ceilings = 4600 SQM
Demountable Double Glazed Partition = 125 LM
Demountable Partitions = 160 LM
Switch Glass Partitions
Sliding Glass Doors  
Timber Door sets to Demountable Partitions.
Main Contractor = Buckingham Group
Building Use = Head Office, Storage, Distribution and Warehouse.
Project Duration = 33 Weeks
Project Value = 1.1 Million
Description =  This was a new build 6 storey project that was a high specification Head Office for a leading Freight, Distribution and Warehousing Company. We undertook a range of works including the installation of timber doors and demountable switchable glazed partitions.
During construction access to the upper floors of this building was restricted because the curtain walling had already been installed. Despite the project being logistically challenging to load out materials we managed to deliver the project on time and to budget. On this project we also trialled magnetic plaster which gave a far better aesthetic finish than a traditional surface mounted board.
 